On the Module assemble board, you place a piece of paper (to even out the vacuum) then a mechanical Si sensor

-- AndrewBlue - 2011-10-12

Module Gluing

Testing

  • 15 Deg from chiller => 25-29 Deg on Hybrid
  • Vacuum on : Always before connections
  • D/M to 2 resisters to right of DC coupled => OV
  • Use 2M IDC Cable
  • Connect to
    • JP38 for Module Testing
    • JP37 for Hybrid Testing

%IMAGE{"Clipboard01.jpg" type="frame" align="none" caption="caption text" }%